| Name of Project : |
Dukhan Housing Project Phase VII(Package 1,2,3) |
| Owner/ Client : |
Qatar Real Estate Investment Company |
| Consultant : |
Consulting Engineering Group (CEG) |
| Location : |
Dukhan, State of Qatar |
| Project Duration : |
631 Days |
| Year Accomplished : |
2010 |
| Project Description : |
Construction of married senior staff bungalow, water tank (Type B) & pump room, External works, Demolition & re-routing works, water tank (Type B & Type C) & pump room, water tank yard, External works, Demolition works, shaded car parking, Hard landscaping works, Soft landscaping works, Infrastructure & demolition works.
|
|
 |
| |
|
| |
| Name of Project : |
Alkhor Housing Project Package 5 |
| Owner/ Client : |
Qatar Real Estate Investment Company |
| Consultant : |
Qatar Design Consortium (QDC) |
| Location : |
Alkhor, State of Qatar |
| Project Duration : |
|
| Year Accomplished : |
2010 |
| Project Description : |
Construction of 50 Nos. of 4 bedroom villas duplex and 2 Nos. of Substation and Infrastructure works including Earthworks, Boundary Wall, Drainage & Service Ducts, Sub Base & Road Base, Flexible Surfacing, Kerbs & Footways, Traffic Signs & Road Markings, QGEWC Water Works, Street Lighting Works, Q-Tel Works, Sewerage Works, Irrigation, Soft Landscaping, Miscellaneous External Works. |
|
 |
| |
|
| |
| Name of Project : |
Ministry of Al Awqaf Compound and office buliding. |
| Owner/ Client : |
Ministry of Al Awqaf and Islamic Affairs / Qatar Islamic Bank (QIB) |
| Consultant : |
Maunsell Consultancy Services, Ltd. |
| Location : |
Consulting Engineering Group (CEG) |
| Project Duration : |
24 Months |
| Year Accomplished : |
2009 |
| Project Description : |
Construct complete infrastructure & buildings as described in the project specifications, contract documents and drawings including structural, architectural, mechanical, electrical works installation, and external works which includes roads, parking areas and landscaping |
|
 |
| |
|
| |
| Name of Project : |
Al Khor Housing Project Package - 4 |
| Owner/ Client : |
Qatar Real Estate Investment Company |
| Consultant : |
Maunsell Consultancy Services, Ltd. |
| Location : |
Alkhor, State of Qatar |
| Project Duration : |
20 Months |
| Year Accomplished : |
2009 |
| Project Description : |
4 type buildings & infrastructure, 62 apartment buildings, 142 villas, a total of 900 flat residential units with complete infrastructure works such as roads, water supply, irrigation system, sewage & drainage works, electrical & substations, telecommunication works, soft and hard landscaping, play areas, etc |
|
 |
| |
|
| |
| Name of Project : |
Mesaieed Housing Project |
| Owner/ Client : |
Qatar Real Estate Investment Company |
| Consultant : |
Maunsell Consultancy Services, Ltd. |
| Location : |
Mesaieed, State of Qatar |
| Project Duration : |
20 Months |
| Year Accomplished : |
2008 |
| Project Description : |
Construction of 262 units of the following types: 177–type A, 12–type B, 24–type C, 33-type C1 including complete infrastructure works such as roads, water supply, irrigation system, sewage & drainage works, electrical works, substations, telecommunication works, soft & hard landscaping, play areas, etc.
|
|
 |
| |
|
| |
| Name of Project : |
Mesaieed Labour Accomodation phase-2 |
| Owner/ Client : |
Qatar Real Estate Investment Company |
| Consultant : |
United Consultants |
| Location : |
Mesaieed, State of Qatar |
| Project Duration : |
9 Months |
| Year Accomplished : |
2005 |
| Project Description : |
Reinforced concrete buildings associated with services and external works including complete infrastructure such as roads, water supply, irrigation system, sewage & drainage works, electrical works, substations, telecommunication works, soft and hard landscaping. |
|
 |
|
| |
|
| |
| Name of Project : |
Ras Gas Housing Project |
| Owner/ Client : |
Qatar Real Estate Investment Company |
| Consultant : |
Dar Al-Handasah Shair and Partners / Qatar Design Consortium (QDC) |
| Location : |
State of Qatar |
| Project Duration : |
24 Months |
| Year Accomplished : |
2002 |
| Project Description : |
Package 6 (74 Villas) is comprised of 45 type BC villas, 16 type B villas, 4 type A+ villas, 2 type A villas and 7 type AB villas as described in the project specifications, contract documents and drawings including structural, architectural, electrical works installation, and external works which includes roads, parking areas and landscaping. |
|
 |
|
| |
|
|
| |
Medical and Educational Institutes |
| Name of Project : |
Learning Center for Qatar Foundation |
| Owner/ Client : |
Qatar Foundation |
| Consultant : |
ASTAD Project Management. |
| Location : |
Al Rayyan |
| Project Duration : |
18 Months |
| Year Accomplished : |
2011 |
| Project Description : |
The works comprise Labor, Services, Supervision, Testing, Equipment, Tools, Supply, Installation, Construction, Testing and Commissioning, All architectural, civil and structural works, All Furniture, Fittings & Equipment (FF&E), All building services and utilities, Tie-in of all building services with the existing site utilities, Tie-in with the existing roads network. |
|
 |
|
| |
|
| Name of Project : |
Mesaieed International School |
| Owner/ Client : |
Qatar Real Estate Investment Company |
| Consultant : |
Maunsell Consultancy Services, Ltd. |
| Location : |
Mesaieed, State of Qatar |
| Project Duration : |
14 Months |
| Year Accomplished : |
2009 |
| Project Description : |
Complete building setup from infrastructure and external works which includes roads, parking areas and landscaping to building construction, electrical works installation, plumbing, internal works, structural and architectural works as described in the project specifications, contract documents and drawings |
|
 |
|
| |
| |
|
| |
| Name of Project : |
Mesaieed Community School |
| Owner/ Client : |
Qatar Real Estate Investment Company |
| Consultant : |
Maunsell Consultancy Services, Ltd. |
| Location : |
Mesaieed, State of Qatar |
| Project Duration : |
14 Months |
| Year Accomplished : |
2009 |
| Project Description : |
Complete building setup from infrastructure and external works which includes roads, parking areas and landscaping to building construction, electrical works installation, plumbing, internal works, structural and architectural works as described in the project specifications, contract documents and drawings. |
|
 |
|
| |
| |
|
| |
| Name of Project : |
Al Gharafa Elementary School of Girls |
| Owner/ Client : |
Building Engineering Department (BED) |
| Consultant : |
GHD |
| Location : |
Al Gharafa, State of Qatar |
| Project Duration : |
15 Months |
| Year Accomplished : |
2005 |
| Project Description : |
Complete building setup from infrastructure and external works which includes roads and landscaping to building construction, electrical works installation, plumbing, internal works, structural and architectural works as described in the project specifications, contract documents and drawings. Also includes construction of a substation, guardhouse, garden house, pump room, sports courts, pavements, shade structures, parking areas and boundary walls. |
|
 |
|
| |
|
| |
| Name of Project : |
International School of Choueifat |
| Owner/ Client : |
Qatari Educational Group |
| Consultant : |
Khatib & Alami |
| Location : |
Dafna, Doha, Qatar |
| Project Duration : |
18 Months |
| Year Accomplished : |
2004 |
| Project Description : |
Reinforced concrete building including MEPD associated works with complete building setup from infrastructure and external works which includes roads and landscaping to building construction, internal works, structural and architectural works as described in the project specifications, contract documents and drawings. |
|
 |
|
| |
|
| |
| Name of Project : |
Salah El Din Ayoubi Preparatory School |
| Owner/ Client : |
Building Engineering Department (BED) |
| Consultant : |
GHD Consultants |
| Location : |
Doha, State of Qatar |
| Project Duration : |
10 months |
| Year Accomplished : |
2004 |
| Project Description : |
Reinforced concrete building with complete setup from infrastructure and external works which includes roads and landscaping to building construction, electrical works installation, plumbing, internal works, structural and architectural works as described in the project specifications, contract documents and drawings. |
|
 |
|
| |
|
| |
| Name of Project : |
Al Doha Preparatory School |
| Owner/ Client : |
Building Engineering Department (BED) |
| Consultant : |
Arab Engineering Bureau (AEB) |
| Location : |
Doha, State of Qatar |
| Project Duration : |
10 months |
| Year Accomplished : |
2004 |
| Project Description : |
Reinforced concrete building with complete setup from infrastructure and external works which includes roads and landscaping to building construction, electrical works installation, plumbing, internal works, structural and architectural works as described in the project specifications, contract documents and drawings. |
|
 |
|
| |
|
| |
| Name of Project : |
Mesaieed Medical Center |
| Owner/ Client : |
Qatar Real Estate Investment Company |
| Consultant : |
Qatar Design Consortium (QDC) |
| Location : |
Mesaieed, State of Qatar |
| Project Duration : |
12 months |
| Year Accomplished : |
2003 |
| Project Description : |
Medium-size medical center to accommodate and serve the Mesaieed residents which includes infrastructure works such as water supply, irrigation system, sewage & drainage works, electrical works, substations, telecommunication works, soft and hard landscaping. |
|
 |
|
| |
|
|
| |
Sports Arenas & Facilities |
| |
| Name of Project : |
Camel Racing Committee |
| Owner/ Client : |
Al-Hejen Racing Committee |
| Consultant : |
|
| Location : |
State of Qatar |
| Project Duration : |
48 months |
| Year Accomplished : |
2007 |
| Project Description : |
Maintenance that includes grading, leveling, electro-mechanical works, soft and hard landscaping, irrigation works, roof structure and miscellaneous civil and external works. |
| |
|
 |
|
|
| |
| Name of Project : |
QATAR SPORTS CLUB PROJECT |
| Owner/ Client : |
Qatar National Olympic Committee |
| Consultant : |
Arab Consulting Engineers |
| Location : |
Doha, Qatar, Al Ettihad , Al Rayyan and Al Wakrah |
| Project Duration : |
18 months |
| Year Accomplished : |
2005 |
| Project Description : |
The project consists of construction of 4 nos.
sports training halls located at Qatar Sports Club, Al Ettihad Sports Club, Al
Rayyan Club and Al Wakrah Club which includes construction of two storey
buildings structural concrete, with a total area of 2700 m2 (area 1 & 2).
The project includes construction of new multi-purpose training hall building
with an approximated total area of 5170 m2. |
|
 |
|
| |
|
| |
| Name of Project : |
Hamad Aquatic Center |
| Owner/ Client : |
Khalifa Sports Development Committee |
| Consultant : |
Dar Al-Handasah Shair and Partners / Projacs |
| Location : |
Khalifa Sports City, State of Qatar |
| Project Duration : |
18 Months |
| Year Accomplished : |
2006 |
| Project Description : |
Construction completion, commissioning and maintenance of a major aquatic center which includes complete building setup from infrastructure and external works to electrical works installation, plumbing, internal works, structural and architectural works as described in the project specifications, contract documents and drawings. |
|
 |
| |
|
| |
| Name of Project : |
Women's Club Sports hall Package-2 |
| Owner/ Client : |
Khalifa Sports City Development Committee |
| Consultant : |
The Arab Architects |
| Location : |
Khalifa Sports City, State of Qatar |
| Project Duration : |
9 Months (Structure Only) |
| Year Accomplished : |
2005 |
| Project Description : |
Concrete structure building covered by steel and an aluminum dome that provides a range of different sports facilities and spa exclusively for women.
|
|
 |
|
| |
|
|
| |
Hotels |
| |
| Name of Project : |
Ramada Hotel |
| Owner/ Client : |
Ramada Hotel |
| Consultant : |
W.S. Atkins & Partners Overseas |
| Location : |
Doha, State of Qatar |
| Project Duration : |
18 Months |
| Year Accomplished : |
2007 |
| Project Description : |
Construction completion and maintenance of a new ten-story hotel building with complete building setup from infrastructure and external works which includes roads and landscaping to building construction, electrical works installation, plumbing, internal works, structural, architectural and mechanical works as described in the project specifications, contract documents and drawings. |
|
 |
|
|
|
| |
Historical Palaces Restoration |
| |
| Name of Project : |
Al Wakra, Umm Sala & Al Gharafa |
| Owner/ Client : |
National Council for Culture, Arts & Heritage, Abdallah Al Thani, Historical Villa, Building Engineering Department (BED)
|
| Consultant : |
Arab Engineering Bureau (AEB) / Davis Langdon |
| Location : |
Doha, State of Qatar |
| Project Duration : |
12 Months |
| Year Accomplished : |
2004 |
| Project Description : |
Miscellaneous works associated with the restoration, renovation, preservation and maintenance of historical buildings that reflects Qatar’s heritage & history. |
|
 |
|
|
|
| |
Worshipping Places |
| |
| Name of Project : |
Fanar Islamic Cultural Center |
| Owner/ Client : |
Ministry of Al Awqaf and Islamic Affairs
|
| Consultant : |
GHD |
| Location : |
Doha, State of Qatar |
| Project Duration : |
18 Months |
| Year Accomplished : |
2005 |
| Project Description : |
A centre dedicated to the Islamic culture that consists of a basement, ground floor and eight floors which works comprises construction completion and maintenance with complete building setup from infrastructure and external works with electrical works installation, mechanical, plumbing, internal works, structural and architectural works as described in the project specifications, contract documents and drawings |
|
 |
|
| |
|
| |
| Name of Project : |
Mosques Project |
| Owner/ Client : |
Qatar Real Estate Investment Company |
| Consultant : |
Qatar Design Consortium (QDC) |
| Location : |
Doha, State of Qatar |
| Project Duration : |
4 months |
| Date Accomplished : |
2002 |
| Project Description : |
Two community mosques at Al Khor for Qatar Gas & Ras Gas which works comprises construction completion and maintenance with complete building setup from infrastructure and external works with electrical works installation, plumbing, internal works, structural and architectural works as described in the project specifications, contract documents and drawings. |
|
 |
|
| |
|
|
High-Rise Buildings |
| |
| Name of Project : |
Al Alawi Tower |
| Owner/ Client : |
His Excellency, Mr. Yousef Al Alawi
|
| Consultant : |
Arab Engineering Bureau (AEB) |
| Location : |
Doha, State of Qatar |
| Project Duration : |
20 Months |
| Year Accomplished : |
2008 |
| Project Description : |
Construction completion & maintenance of a nineteen-story office building along with all services and other MEPD associated works and infrastructure facilities with external works to building construction, structural and architectural works as indicated in the drawings & project specifications. |
|
 |
|
| |
|
| |
| Name of Project : |
QREIC Tower |
| Owner/ Client : |
Qatar Real Estate Investment Company
|
| Consultant : |
KEO International Consultants |
| Location : |
Doha, State of Qatar |
| Project Duration : |
18 Months |
| Year Accomplished : |
2008 |
| Project Description : |
Construction completion & maintenance of 2B + G + M + 14 floors—Qatar Real Estate Investment Company office building along with all services and other MEPD associated works and infrastructure facilities with external works to building construction, structural and architectural works as indicated in the drawings & project specifications. |
|
 |
|
| |
|
| |
| Name of Project : |
Beverly Hills Tower |
| Owner/ Client : |
Al Asmakh Contracting
|
| Consultant : |
GHD |
| Location : |
Doha, State of Qatar |
| Project Duration : |
20 Months |
| Year Accomplished : |
2006 |
| Project Description : |
Construction completion and maintenance of a tower that consists of a basement, ground floor, first floor, club house, 26 floors and two penthouse floors along with all services and other MEPD associated works and infrastructure facilities with external works to building construction, structural and architectural works as indicated in the drawings & project specifications. |
|
 |
|
| |
|
| |
| Name of Project : |
AL Sulaite Office Tower - 2 |
| Owner/ Client : |
Qatar Islamic Bank (QIB) |
| Consultant : |
GHD Consultants |
| Location : |
Doha, Qatar |
| Project Duration : |
18 months |
| Date Accomplished : |
2004 |
| Project Description : |
An office building consisting of a basement, ground floor + 15 floors with all services and other MEPD associated works and infrastructure facilities with external works to building construction, structural, architectural and all electro-mechanical works as indicated in the drawings & project specifications. |
|
 |
|
| |
|
|
Infrastructure & Earthworks |
| |
| Name of Project : |
West Bay Road Works and Infrastructure |
| Owner/ Client : |
ASHGHAL (Public Works Authority)
|
| Consultant : |
SMEC |
| Location : |
West Bay, State of Qatar |
| Project Duration : |
|
| Year Accomplished : |
2011 |
| Project Description : |
Construction of road network and infrastructure of approximately 12.1 km of roads in the New Diplomatic Area named as Zone 66 which works include complete infrastructure such as electrical works, storm drainage, Q-Tel, service water, TSE lines, soft and hard landscaping and irrigation with advanced security elements and associated works for the Embassies including security wall, CCTV cameras, gates, fiber optic cables, road blocks, security rooms, special signage and other necessary security items. Additional works comprise 4 units—indoor substation, boundary walls, MCCC buildings and surface water pump stations. |
|
 |
|
| |
|
| |
| Name of Project : |
Barwa Commercial Avenue (Micro-Tunneling) |
| Owner/ Client : |
Barwa / Hochtief
|
| Consultant : |
AECOM Middle East Limited |
| Location : |
Abou Hamour, State of Qatar |
| Project Duration : |
|
| Year Accomplished : |
2011 |
| Project Description : |
Construction of tunnels that will serve as provisions for the groundwork in laying the waste water and potable water network systems. |
|
 |
|
| |
|
| Name of Project : |
Barwa Commercial Avenue (Bulk Excavation) |
| Owner/ Client : |
Barwa / Hochtief
|
| Consultant : |
Maunsell Consultancy Services, Ltd. |
| Location : |
Doha, State of Qatar |
| Project Duration : |
|
| Year Accomplished : |
2010 |
| Project Description : |
Excavation up to the sub base level of the permanent roads and parking areas based on project specifications, subcontract documents and drawings. |
|
 |
|
| |
|
| Name of Project : |
Barwa Commercial Avenue (Excavation & Bliding) |
| Owner/ Client : |
Barwa / Hochtief
|
| Consultant : |
Maunsell Consultancy Services, Ltd. |
| Location : |
Doha, State of Qatar |
| Project Duration : |
|
| Year Accomplished : |
2009 |
| Project Description : |
The works entailed the breaking, loosening, excavation, loading, hauling and tipping of all materials related to defined excavation for the substructure of the underground parking spaces for building type 1, type 2, type 3, type 4 and type 5, as shown in the drawings and project specifications. Also includes the placement of a blinding layer below the basement slabs and isolated basement footings. |
|
 |
|
| |
|
| |
| Name of Project : |
Barwa Commercial Avenue (Backfilling) |
| Owner/ Client : |
Barwa |
| Consultant : |
Maunsell Consultancy Services, Ltd. |
| Location : |
Doha, State of Qatar |
| Project Duration : |
48 months |
| Date Accomplished : |
2008 |
| Project Description : |
Enabling works of Barwa Commercial Avenue comprise the following, Site clearance, removal of debris and dumped material from the commercial strip and disposal to approved tip offsite, Bulk backfilling works to raised plot platform between 0.5 to 0.75m above existing road level, Main site offices, Hoarding for the entire site and Advertising sign boards |
|
 |
|
| |
|
|
Roadworks and Pavement Projects. |
| |
| Name of Project : |
Road Works and Pavement Projects |
| Owner/ Client : |
|
| Consultant : |
|
| Location : |
Doha, State of Qatar |
| Project Duration : |
9 Months |
| Year Accomplished : |
2003 |
| Project Description : |
Infrastructure and external works comprise of roads, hard landscaping and structural works for different miscellaneous road projects as described in project specifications and contract documents. |
|
 |
|
|
| |
|
Top |
|
|
|
|
|
|